Estimate your construction schedule phase-by-phase based on house size, floors, and finish level.

Estimated Duration

~12 months

Planned Start

Oct 2026

Estimated Completion

Oct 2027

Construction Phases

Site Preparation1 wk–2 wk· Oct 2026

Demolition, clearing, levelling, and setting out.

Excavation & Foundation4 wk–1.8 mo· Oct 2026

Excavation, footings, raft/strip foundation pouring and curing.

Plinth Beam & DPC1 wk–2 wk· Nov 2026

Plinth beam construction and damp-proof course application.

Superstructure (per floor)2.8 mo–4.6 mo· Dec 2026

Brick masonry, RCC columns, beams, and slab per floor.

Roof Slab & Waterproofing2 wk–4 wk· Apr 2027

Final slab pour, curing, and waterproofing membrane application.

Plumbing & Electrical Rough-in3 wk–5 wk· Apr 2027

Concealed plumbing and electrical conduit work within walls.

Plastering4 wk–7 wk· May 2027

Internal and external plastering. Two coats for external surfaces.

Flooring2 wk–4 wk· Jul 2027

Tile or stone flooring installation throughout.

Woodwork3 wk–5 wk· Jul 2027

Door frames, doors, windows, and built-in cabinetry.

Electrical & Plumbing Fit-out2 wk–3 wk· Aug 2027

Switches, sockets, fixtures, taps, and sanitary ware installation.

Painting2 wk–4 wk· Sep 2027

Interior emulsion and exterior weather-resistant paint.

Final Finishing & Cleanup1 wk–2 wk· Sep 2027

Snagging, touch-ups, site cleanup, and handover preparation.

Darker bar = estimated midpoint duration. Lighter bar = maximum estimate. Monsoon season (June–September) typically slows outdoor work by 20–30%. Add 4–8 weeks of buffer for weather, material delays, and approvals.